Solar performance ratio, or PR, compares measured PV output with the output implied by the installed DC nameplate capacity and the sunlight received in the array plane. A cloudy roof can produce fewer kilowatt-hours and still have a similar PR to a sunny roof. Lower energy by itself cannot tell you whether weather, the plant or the measurement caused the difference.

This guide uses conventional AC PR for a grid-connected PV system without storage in the measurement boundary. For an integrated PV and battery system, establish a separate PV production meter or an agreed equivalent calculation. Grid export and facility net consumption are not substitutes for total PV production.

Use matching dates and measurement points

Three inputs are enough for a basic calculation, provided they describe the same system and period.

Input Meaning Example
Measured AC energy PV production at the declared AC meter 9,600 kWh
Installed DC rating Nominal module ratings summed for that plant 100 kWp
Plane-of-array irradiation Period sunlight integrated at the array plane 120 kWh/m²

The daily or period final yield is the AC energy divided by installed DC power. In the example this is 9,600 kWh divided by 100 kWp, or 96 kWh/kWp. The reference yield is the measured irradiation divided by the reference irradiance of 1 kW/m². Here it is 120 hours. Dividing final yield by reference yield gives 96 / 120 = 0.80, or 80% PR. You can also multiply the 100 kWp rating by the 120 reference hours to get a reference energy of 12,000 kWh, then divide 9,600 by 12,000.

Worked performance ratio calculation uses 9,600 kWh measured AC energy and 12,000 kWh reference energy.
Worked performance ratio calculation uses 9,600 kWh measured AC energy and 12,000 kWh reference energy.

The Sandia PV Performance Modeling Collaborative describes the AC and reference yields. The numerical example is hypothetical. A weather service’s horizontal irradiation estimate is not automatically equivalent to a measurement in the roof plane. Multiple roof orientations may need representative sensors or a documented composite approach.

Distinguish PR from the other numbers on a dashboard

Production in kWh answers how much electricity the system delivered in the period. Specific yield in kWh/kWp makes output easier to compare across plant sizes, but two areas can have very different sunlight. Performance ratio adds an irradiance reference. Availability describes whether equipment or capacity was available according to a defined rule. A project can have high availability and still exhibit reduced yield.

For another hypothetical month, suppose the same 100 kWp rooftop records 90 kWh/m² of plane-of-array irradiation and produces 7,200 kWh AC. Its reference energy is 9,000 kWh, and its PR is still 80%. Output fell relative to the first example because the irradiation was lower in these simplified inputs. This does not mean equal PR proves that nothing changed. Separate losses can offset one another, and both months could contain measurement errors.

Two hypothetical months have different AC production but the same 80% ratio after normalization.
Two hypothetical months have different AC production but the same 80% ratio after normalization.

Avoid averaging daily percentages as if all days carried the same weight. On two hypothetical days with reference energies of 100 kWh and 300 kWh and actual energies of 70 kWh and 255 kWh, the daily values are 70% and 85%. The pooled ratio is 325 divided by 400, or 81.25%. An unweighted mean gives 77.5%. Use the method specified in the contract or report, and label any missing data so the calculation can be reproduced.

Troubleshoot a lower ratio from the inputs outward

  1. Validate the measurement window. Check time zone, missing intervals, resets, plant capacity changes, commissioning dates and meter boundaries. Exclude or flag periods with incomplete data consistently. Moving an inverter to a different meter or summing both inverter logs and a plant meter can create a false change.
  2. Check the irradiance evidence. Confirm the sensor plane, calibration status, cleanliness, shading and gaps. A shaded sensor can artificially raise PR even when the panels are producing less. Treat a result above an expected range as a reason to review inputs, not automatic evidence of exceptional hardware.
  3. Review operation and weather. Hot modules can produce less DC power under the same incident light. Soiling, snow where relevant, shading, clipping, grid restrictions or outages can also affect output. A weekday export cap and a weekend dip might come from different causes. Compare power, irradiance, temperature and event logs on the same timestamps.
  4. Match the loss to a time pattern. A midday plateau may be consistent with clipping or a power limit, while a recurring drop on one input can suggest a string-level problem. A sudden PR change affecting every inverter at exactly the same time may justify checking the common meter or an operating command before looking for panel faults.
  5. Compare the right baseline. Compare periods with similar weather or use a documented temperature or weather correction when appropriate. Keep the conventional PR and any corrected version labelled separately.
A diagnostic order for checking data, site operation and comparable baselines after a performance ratio change.
A diagnostic order for checking data, site operation and comparable baselines after a performance ratio change.

The guide to hot-roof module temperature coefficients helps with temperature hypotheses. Compare the shape of an AC power plateau with the inverter clipping guide. If cleaning is being considered, use the Philippine solar panel cleaning guide to plan before-and-after evidence instead of assuming every drop comes from dirt.

Define the ratio before putting it in a contract

If an EPC or operations agreement calls for a PR threshold, agree on the metering boundary, sensor data, monitoring period, allowed exclusions, treatment of curtailment and missing data, and whether the ratio will be weather corrected. A technical report should identify the rated DC capacity and how changes to it will be handled. Ask who owns data quality and how a gap is documented. A number with no method may be difficult to reproduce during an acceptance or performance dispute.

Some projects install batteries or limit export. A retail meter may then show little export while the array is supplying onsite demand or charging storage. Likewise, PV power that an inverter is instructed not to produce can reduce measured output relative to the irradiation. Reconstruct the PV-side measurement and label control events before attributing a lower ratio to equipment degradation. Where a single sensor cannot represent several roof faces or more than one row configuration, write down the reference model before comparing sites.

Prepare a short report that another analyst can reproduce

List the date range and time zone, connected kWp, meter ID and boundary, delivered kWh, plane-of-array irradiation, calculation method, flag rules and any known outages. Attach daily values or source files, then separate observations from possible causes. For example, report that production flattened at a certain time and the control log showed an export limit, rather than assigning all annual loss to one screenshot.

If the site expanded during the comparison period, break the calculation into intervals with a consistent configuration rather than using the final capacity against the entire month’s energy. A meter swap or cleaning of the irradiance sensor also deserves an annotation. Keep the raw series intact and document exclusions alongside the reported result. The person reviewing next month’s figures should be able to reproduce this month’s value without depending on a screenshot of an old dashboard.

If equipment checks are necessary, share interval production, irradiance, temperatures and operating logs with GINZA Power. The best next step depends on whether the divergence is in the readings, the operation of the plant, or the physical equipment.

When a project is still being designed, compare roof direction and panel tilt using the site weather before interpreting the modeled output.